Uitspraak
GERECHTSHOF DEN HAAG
Arrest d.d. 31 mei 2016
Waagner Biro Bridge System AG,
A-Lanes Civil VOF,
advocaat: mr. D. Timmermans te Zeist.
Het verdere geding
De beoordeling van het hoger beroep
“(…) CIVIL VOF(bedoeld is: A-Lanes)
hereby award Contractor(bedoeld is
: Waagner Biro) the contract for Part 2 (Design, Construct, and Installation of the M&E of the Botlek Bridge) as further specified in the Contract and the Scope of Works.”
The Contractor shall design, execute and complete the Works in accordance with the Agreement, and shall remedy any defects in the Works. When completed, the Works shall be fit for the purposes for which the Works are intended as defined in the Agreement. The Contractors shall be deemed to have scrutinized the CIVIL VOF’s Requirements (in particular as specified in Annex 2 and 3, for example the DO-Design), including design criteria and calculations if any. The Contractor shall be responsible for the design of the Works and for the accuracy of CIVIL VOF ‘s Requirements (in particular as specified in Annex 2 and 3; for example the DO Design).(...)
If errors,
zonder meergehouden kan worden aan de inhoud van de planning te voldoen. Vervolgens komt de overweging over het door partijen gezamenlijk bepalen wat en op welk moment zal worden uitgevoerd. Voor zover Waagner Biro nog betoogt dat zij slechts tot uitvoering van de werkzaamheden kan worden verplicht hetzij na een uitdrukkelijke opdracht bij meerwerk, hetzij na uitdrukkelijk gegeven instructies met betrekking tot meerwerk of “additional works’ in lijn met de Variations procedure, verliest zij uit het oog dat zij op grond van het vonnis bij wijze van voorlopige voorziening wordt veroordeeld tot het uitvoeren van (alle) werkzaamheden, zodat een opdracht of instructies als bedoeld niet aan de orde zijn.
Uit het voorgaande vloeit voort dat het bestreden vonnis moet worden bekrachtigd. Beslist zal worden als na melden.