2.13.Op 19 februari 2021 zijn partijen ’s ochtends samen door de woning gelopen. Direct daarna heeft [gedaagde] eisers daarover het volgende gemaild:
As discusses, we have finished the work today.
You have delivered every room with [Naam 2] and it is nog the intention that after the delivery all notes or comments arise that something is wrong or not yet right. Otherwise we are never finished this way.
It is an old house and nothing is straight, so we cannot make all the plasterwork 100% straight /level. That is impossible.
My men checked everything and it cost me around € 20.000,- to make al the changes.
We couldn’t get it better at a given moment.
As mentioned earlier, the delivery of stuccowork with a construction lamp or flashlight, isn’t in the way we do that in the Netherlands.
If we would do that, no wall will be tight of flat, never.
We have done everything we can to make it as good as possible.
Aan het eind van die middag hebben eisers daarop geantwoord:
Indeed, we need to stop at one point so that we can all move on.
Your team left earlier this afternoon and we made a round with them to check their work.
There are however two points not related to carpentry/painting for which we still need you:
1. We just made a check on the internet sockets and unfortunately two of them are not working: one in the studyroom (wall facing the street) and the other one in the hobby room (wall shared with the garage). Can the electrician pass to fix this?
2. Do you have any news from the plumber regarding the bubbling noise in our kitchen? He was mentioning a full check to assess the situation.
We need to meet all together for the final bill and for going through the more/less quotation.
During this meeting we will discuss the points that you mentioned in your email here below, as well as other defects we previously mentioned.
In particular, your team should have told you today about the additional problem we noticed about the slope in the new fake-ceiling of the entrance/corridor.
In order to be complete for this meeting, we asked a controller to come check the house (“Bouwtechnische keuring na verbouwing”). This visit will take place in the first week of March.
Would it be then possible to have our meeting around the 8th of March?
[gedaagde] antwoordde per ommegaande – kort gezegd – dat de loodgieter de dinsdag erop kon langskomen, dat eventueel restgeluid in de keuken kon worden opgelost door een gat naar het dak te maken, dat [gedaagde] nog iets aan het valse plafond wilde doen, en dat 8 maart perfect uitkwam voor de bespreking.